# 136

Storm Damage

By June 2021, Public Works will initiate construction on 20% of the 170 storm damaged sites remaining to be repaired from the 2016/2017 storms.

VERIFICATION LINK/DOCUMENTATION

Key Steps

1 2 3 4
Secure required funding and budget for the repairs. Secure all required construction permits from the regulatory agencies. Complete Plans, Specifications and Estimate (PS&E) package and obtain permission to advertise projects. Advertise projects, open bids and award contracts.
Plan Reference: Collaborating Depts:
Target:
Baseline: Progress:
3.C.ii HSA 34 Storm Recovery Projects 1 133% (45)